Greenfield Turnkey Project – Major Equipment Fabrication & Supply
Successfully executed a Greenfield Turnkey Project with complete design, fabrication, and supply of:
- 500 KL SS Storage Tank – 1 No.
- 300 KL SS Storage Tanks – 2 Nos.
- 60 KL Underground Tanks – 3 Nos. (SA-516 Gr. 70)
- 30 KL Reactors – 3 Nos. (with Limpet Jackets & Agitators)
- Screw Conveyors – 2 Nos. (25m each)
- Pressure Vessels – Multiple (2 KL to 10 KL)
- Heat Exchanger – 1 No. (50 m², SS316L)
- Piping, Hoppers, Bag Filters & Accessories
All equipment complied with ASME & IS standards, underwent 100% radiography, and was inspected by leading TPI agencies.